Brief Summary

The Beaver Water Surge tank was a dynamic, collaborative project that involved the installation of a new surge tank and pad. Initially BWD had sourced the surge tank from a specialized surge tank manufacturer with a quoted lead time of 30+ weeks. Crossland Heavy was able to utilize it’s existing relationship with a supplier to supply the tank in <16 weeks at a significant cost savings to BWD.

This allowed the tank to be installed in a timely manner and the project to complete ahead of schedule and under budget. 

Project facts

  • Client - Beaver Water District
  • Engineer - Olsson (Formerly: McGoodwin Williams & Yates)